4-3 Traffic

How many trucks will be traveling Town roads during construction of this project?

RESPONSE 4-3:

 

Truck traffic during construction will vary depending on the phase of the project.  The estimated number of trucks that will access the site for various phases of construction are listed below:

 

A.  Mobilization Phase:  an average of 12 trucks per day.

B.  Underground Work Phase:  an average of 15 trucks per day.

C.  Aboveground Work and Equipment Delivery Phase:  an average of        

      15 trucks per day.

D.  Demobilization Phase:  an average of 12 trucks per day.

 

Further details on the anticipated truck traffic are included in Section 6.8 of the EFSB Application.  Invenergy Thermal Development LLC (“Invenergy”) is having a traffic study prepared that will be provided to the Town of Burrillville when it is completed.

 

RESPONDENT:

 

John Niland, Invenergy Thermal Development LLC

Maureen Chlebek, McMahon and Associates

 

DATE:

April 27, 2016