6-5 Traffic

Is there a plan to repair roads damaged by traffic from construction?

RESPONSE 6-5:

 

A baseline inventory of pre-construction roadway conditions is already underway, and is focused on Route 100 in Burrillville and Glocester.  Coordination has been initiated with the Rhode Island Department of Transportation (“RIDOT”) regarding the assessment.  Upon completion of construction, any further deterioration or damage beyond what would normally be expected will be assessed in coordination with RIDOT. 

 

RESPONDENT:

 

Maureen Chlebek, McMahon Associates

 

DATE:

May 11, 2016