Storm Water: 4-15

The site appears to be creating a large amount of impervious space. Is this correct? Please explain the site’s storm water management plan. Has a storm water report been done? If so, please provide a copy. Will the detention basins handle a one

Based on the current general arrangement and conceptual site grading plan, impervious areas are anticipated.  The stormwater management plan is currently being developed and will comply with RIDEM regulations including best management practices, including complying with the 100-year, 24-hour stormwater attenuation criteria.  A copy of the stormwater report will be provided upon completion.