Provide the following annual data:

Provide the following annual data:

  • Annual number of MWH the CREC is anticipated to produce operated on natural gas between 2019 and 2038 broken down by calendar year;
  • Annual number of MWH the CREC is anticipated to produce operated on ultra-low sulfur distillate ("ULSD") between 2019 and 2038 broken down by calendar year;
  • Annual cost of water in $/MWH added to the variable cost of the unit when firing ULSD.

     

  • The MWhs provided below were based on the previously provided confidential PA Consulting, Inc. forecast. The forecasted MWhs listed below are confidential.

    [TABLE REDACTED]

  • Neither Invenergy nor PA has calculated the annual number of MWh CREC is anticipated to produce when operated on ultra-low sulfur distillate between 2018 and 2038 broken down by calendar year. In summary, absent discrete gas shortage events (which are random events which cannot be forecast), PA does not project CREC to utilize ULSD.
  • Invenergy has not calculated the annual cost of water in $/MWh added to the variable cost of the unit when firing ULSD.