5-2 Construction

Please identify the exact water pipe line route and plans for construction.

RESPONSE 5-2:

 

The ground survey for the new pipeline route has begun and should take approximately 5 weeks to complete. Invenergy will proceed with the development of the design plans at survey completion. The geotechnical borings are scheduled to begin on May 5, 2016 and should take approximately 7 days to complete. Exact water pipe line route and plans will take some time to develop.

 

Please see the proposed water pipe line route, attached as Exhibit 1.

 

RESPONDENT:

 

John Niland, Invenergy Thermal Development LLC

DATE:

April 28, 2016