EFSB Orders
The Energy Facility Siting Board (EFSB) issued its Preliminary Decision and Order on March 10, 2016. Included in the Preliminary Decision and Order was an explanation and list of advisory opinions required by the EFSB.
We’ve been asked to link directly to this information to make it easier for the public to find specifics.
Here is a link to the Preliminary Decision and Order
The following table shows the list of agencies and individuals who have been ordered to provide advisory opinions. You can find the specifics of the directive on the pages noted in the table. The table is being updated as hearings are scheduled and opinions are submitted to the EFSB. As always, full details can be found on the EFSB web pages dedicated to this application.
Public Utilities Commission | Page 15 | The evidentiary hearing will commence on Monday, July 25, 2016 @ 9:30 a.m. | |
Statewide Planning Program | Page 16 | ||
Office of Energy Resources | Page 17 | Scheduled for July 21, 2016 | |
Department of Health | Page 16 | Rhode Island Department of Health's draft advisory opinion on the Invenergy proposal | Hearing for public comment on the draft has been scheduled for August 9, 2016 |
Burrillville Planning Board | Page 16 | Planning Board Advisory | August 15, 2016 |
Department of Environmental Management | Page 14 | Advisory Opinion | |
Burrillville Zoning Board of Review | Page 13 | Zoning Board Advisory | |
Burrillville Building Inspector | Page 14 | Building Official's Opinion | |
Historical Preservation & Heritage Commission | Page 14 | ||
Department of Transportation | Page 14 | Advisory Opinion | |
Burrillville Tax Assessor | Page 17 | Assessor's Advisory | |
Pascoag Utility District | Page 17 | PUD Advisory |
On October 3, 2016, the Energy Facility Siting Board issue a Show Cause Order that "Invenergy shall appear before the Board on October 13, 2016 at 12:00 pm to show cause why the licensing proceedings should not be suspended". Follow this link to view the entire order.