What is the output production rating of the defunct Pascoag Utility District water wells?
RESPONSE 5-16:
| 700 gallons per minute. Pascoag Utility District (“PUD”) Well #3A was originally tested at 700 gallons per minute (gpm) [1,000,800 gallons per day (gpd)].
|
RESPONDENT:
| Mike Feinblatt, ESS Group, Inc. John Niland, Invenergy Thermal Development LLC
|