5-18 Water

If Pascoag Utility District wells do not meet the demand for the power facility, where will the water come from?

RESPONSE 5-18:

 

Invenergy fully expects that the PUD well will meet the needs for the power facility.  The well’s capacity has been demonstrated in the past.  If the well or treatment system is unavailable due to maintenance or repair, these maintenance cycles will be scheduled to coincide with CREC’s maintenance cycles.  Should the well unexpectantly need maintenance,  Invenergy would rely on the water stored at the CREC site.  If the well outage is longer and causes the entire CREC stored water to be utilized, Invenergy would pursue an alternate supplier.

 

RESPONDENT:

 

John Niland, Invenergy Thermal Development LLC

DATE:

April 28, 2016