DEM timeline
Posted on: August 17, 2016 - 4:33pm
The Department of Environmental Management has announced theh following expected timeline for review of the proposed Invenergy power plant.
- DEM is in the early stages of its review of the application and expects to complete the review in December 2016.
- The permit process does include the opportunity for public comment and a public hearing. It is expected that the public comment/public hearing aspect of the process will occur in February/March 2017.
- A final determination to issue or deny the permit is expected in May 2017.