EFSB Issues Final Order
Energy Facility Siting Board issues final decision and order. You may read the full decision by following this... more ››
Burrillville Submits Objections to CREC's Application to DEM
The Town of Burrillville has submitted comments to Rhode Island Department of Environmental Management's Office of Air Resources to object... more ››
Town of Burrillville Asks Army Corps of Engineers to REQUIRE Environmental Impact Statement for Invenergy Plant
EIS Needed to Consider Environmental, Socio-economic & Cultural Impact
Must Also Include the 8.5 Mile Burrllville Interconnect... more ››
Renewed request for Environmental Statement
July 2, 2019EXPRESS MAILU.S. Army Corps of Engineers
New England District
696 Virginia Road
Concord, MA 01742Attn: Alex... more ››
EFSB Denies Permit
UPDATE:Transcript of the June 20, 2019 EFSB meeting is attached.At an open meeting of the Energy Facility... more ››
EFSB Denies Permit
At an open meeting of the Energy Facility Siting Board (EFSB) held June 20, 2019, the EFSB
DEM Press Release
Press ReleasesDEM to Hold Extended Public Hearing June 19th on Draft Permit for Proposed Clear River Energy Center in... more ››
Revision of Energy Facility Siting Act
The Town of Burrillville is calling for an overhaul of the 30-year old outdated Rhode Island Energy Facility Siting Act and supports Senate... more ››
6-25-19 Open Meeting
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS
ENERGY FACILITY SITING BOARD
NOTICE OF OPEN MEETING
6-21-19 Open Meeting
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS
ENERGY FACILITY SITING BOARD
NOTICE OF OPEN MEETING
6-20-19 Open Meeting
STATE OF RHODE ISLAND AND PROVIDENCE PLANTATIONS
ENERGY FACILITY SITING BOARD
NOTICE OF OPEN MEETING
Burrillville Files Post-Hearing Brief
On May 17, 2019, the Town of Burrillville filed its post-hearing brief with the Energy Facility Siting Board, which is considering the... more ››
Burrillville Police Application Process
Aging Resource Expo
Final Witness Testimony Concludes EFSB Hearing
Final Witness Testimony Concludes EFSB Hearing on
Proposed Invenergy Power Plant
Next - Final Briefs... more ››
Proposed Power Plant
Biodiversity Expert Says Invenergy Power Plant Site is Environmentally One of
Most Valuable in Southern New England
More Rare... more ››
Treasured Rhode Island Resource
With the EFSB final hearings resuming on the proposed Invenergy power plant for Northwestern Rhode Island - it’s a good time to take a... more ››
FERC Accepts ISO NE
165 FERC ¶ 61,137UNITED STATES OF AMERICAFEDERAL ENERGY REGULATORY COMMISSION ISO New England Inc.